Kartarpur Corridor: Pakistan Completes Construction of Bridge Over Raavi River
Kartarpur Corridor: Pakistan Completes Construction of Bridge Over Raavi River
Page Visitors: 2405

Kartarpur Corridor: Pakistan Completes Construction of Bridge Over Raavi River
Posted:
01 Jun 2019 08:32 AM PDTLAHORE, Punjab—In its third official video about Kartarpur corridor project released on May 31, the Pakistan government has revealed that the construction work bridge over the Raavi river has completed and the construction work will also be completed after vacations of Eid.
Sharing the details about ongoing construction work, Engineer Khashif Ali informed that the foundation work of Kartarpur corridor project has been 100% completed while the construction work of building, holy sarovar, Baradari, Guest house etc. is 70% complete. He added that the construction work of Kartarpur corridor project is going on continuously.
Er. Khashif Ali has further informed that the construction work of 4.6 kilometers long road has been also completed up to 95%. “Beside it, the construction work of sewerage, water supply and water outflow is complete around 60%, 55% and 50% respectively,” he said while adding that prickled fence will be installed in 20 Kilometer area for the security of Sikh pilgrims.
It is learnt that the marble installation work in over 10 acres of land around Gurdwara Sri Kartarpur Sahib will be completed by the mid July while the construction work of boundary wall to save Gurdwara premises and the corridor during the floods has been already completed.